Delivering E.ON Drive Infrastructure’s UK Charging Network

E.ON Drive charging network

Delivering E.ON Drive Infrastructure’s UK Charging Network

How The EV Network is delivering a growing network of charging hubs across the UK.

The EV Network (EVN) is the infrastructure delivery partner behind E.ON Drive Infrastructure UK’s (E.ON Drive) high-powered charging network, leading the end-to-end development, construction, commissioning, service and maintenance of its sites. Since the first hub went live in October 2023, the network has grown to 27 live hubs, 99 chargers and 198 charging bays across England, Scotland, Wales and Northern Ireland. EVN is continuing to deliver against an active pipeline that is expected to take the network to approximately 112 live chargers and 224 live bays by the end of 2026.

The partnership has developed as the network has grown. Early challenges at the first site in Teesbay helped the teams refine how they plan and deliver new hubs, while Frome’s 25-working day delivery shows how much that approach has progressed.


Delivering the E.ON Drive Infrastructure Charging Network

  • 27 live charging hubs
  • 99 live chargers and 198 live charging bays
  • More than 30 MVA of connected site and grid capacity
  • Full end-to-end services delivered by EVN including development, construction, commissioning, service and maintenance, and technical support
  • EVN’s current delivery pipeline is expected to take the network to approximately 112 live chargers and 224 live charging bays by the end of 2026

Delivering the E.ON Drive Infrastructure UK Charging Network

EVN manages the work as a coordinated portfolio rather than a series of single projects. Hubs progress through different stages at the same time, requiring close coordination with E.ON Drive, landowners, retailers, distribution network operators, local authorities, contractors and other delivery partners.

EVN’s Infrastructure-as-a-Service (IaaS) model brings these activities together under one delivery structure. EVN takes each site from initial development and legal work through design, construction and commissioning, before continuing into service and maintenance once the hub is operational.

A suite of standard drawings based on E.ON Drive’s technical specification gives each project a common starting point while allowing for different layouts, power requirements and site conditions. EVN’s in-house development, legal, technical, construction and operational teams work across all phases, including grid connections, third-party approvals, payment terminal configuration and the transition into operation. When a change proves effective on site, it can then be considered for the projects that follow.

The hubs are located at retail parks, roadside destinations and F&B locations where drivers already stop. This also includes sites delivered through EVN’s wider relationship with Tim Hortons, where E.ON Drive provides the charging network.

EVN leads the end-to-end development and delivery of the infrastructure behind E.ON Drive’s charging network, while E.ON Drive sets the network requirements and remains closely involved in decisions affecting its sites. Once a hub is operational, EVN continues to provide technical and maintenance services across the network. Regular contact between the teams allows issues to be raised while a project is still moving, rather than held until the next formal stage.

That becomes increasingly important when several sites are at different stages. A legal issue on one project, a commissioning requirement on another and an operational fault at a live hub may all need attention at the same time. Managing them as one portfolio gives both teams a wider view of priorities and allows relevant experience to be shared between projects.

Sam Shaybani, Co-Founder & Chief Operating Officer said:
“From the outset, EVN’s role has been to lead the development and delivery of infrastructure behind E.ON Drive’s UK charging network. Bringing our property, legal, finance, pre-construction, construction and operational teams together has enabled us to deliver 27 live hubs across a wide range of locations and site conditions.

As the portfolio has grown, the working relationship between EVN and E.ON Drive has developed with it. The experience gained across each site has helped both teams make better informed decisions, anticipate challenges earlier and strengthen the way new hubs are delivered and supported. That gives us a strong foundation for the continued growth of the network.”


From Teesbay to Frome

The first hub, at Halfords in Teesbay Retail Park, went live on the 31st October 2023. During delivery, the team identified a water main on the proposed high-voltage cable route that had not appeared in the utility research. EVN redesigned the route and amended the associated substation legal requirements and cable-way lease. The change delayed the project by four months but protected the long-term infrastructure and gave both teams a clearer view of the technical and legal checks required on later sites.

Payment terminal configuration created a further issue near the end of the project. Requirements can differ between sites and systems, meaning E.ON Drive and EVN worked through the configuration before opening the hub. Together, the route redesign and terminal work established practical checks that could be brought forward on later schemes. Verifying physical constraints early, aligning technical and legal changes, and confirming payment requirements before commissioning.

As the portfolio developed, the teams gained a clearer understanding of E.ON Drive’s specification, decision-making requirements and operational priorities. Standard drawings reduced avoidable design variation, while construction and operations shared issues identified on live sites with the teams developing the next projects. This did not remove the need for site-specific decisions, but it gave each project a better starting point.

By April 2026, the difference could be seen at Frome. Works began on the 9th of March, and went live on the 14th of April, only 25 working days after construction started. Frome is the fastest E.ON Drive hub delivered by EVN to date. Every site is different, but the programme shows how experience gained across a portfolio can make later delivery more efficient.

from teesbay to frome

The portfolio has also grown in size. Livingston Fairways Business Park, Gosport Brockhurst Gate Retail Park, Aberdeen Wellington Circle and Dodworth Elmhirst Lane each have 6 chargers and 12 bays, the largest hub format currently delivered in the programme. Livingston also marked EVN’s 200th charger delivered across its wider portfolio. These sites show that the common delivery approach can support larger hubs across different layouts, power supplies and stakeholder environments.

Dev Chana, Managing Director of the UK at E.ON Drive Infrastructure said:
“Delivering a charging programme of this scale across the UK requires a partner that can combine consistency with the flexibility to respond to the individual challenges of each location.

Over the course of our relationship, The EV Network has developed a strong understanding of E.ON’s requirements and worked closely with our teams to overcome challenges, apply lessons across the portfolio and continually improve the way sites are delivered. That collaborative approach has played an important role in building a growing network that we can continue to develop together.”


Delivering & Supporting the Network

Power remains one of the main dependencies. Connection routes, approvals and third-party works require coordination with DNOs, councils and local authorities, often outside the direct control of EVN or E.ON Drive. With more than 30 MVA of connected capacity across the E.ON Drive network, high-voltage infrastructure has formed a substantial part of the programme.

That work includes agreeing connection routes, securing approvals and coordinating third-party activity. A change to the physical design can also affect land rights or legal agreements, as Teesbay demonstrated, so technical and legal workstreams need to progress together. EVN’s legal team works alongside design and construction to resolve these dependencies and prevent an isolated issue from becoming a larger blocker.

Connectivity and payment terminal configuration tend to arise later in delivery, when construction may be substantially complete, but the hub is not yet ready to open. Bringing commissioning and operational teams into the process early helps identify those requirements before handover. Standard configurations and experience from completed sites now give the teams a clearer starting point, while retaining the flexibility needed for each location.

Site conditions and stakeholder dependencies vary, but the standard of construction and long-term resilience of the infrastructure cannot. The teams therefore use a repeatable process while making the technical decisions required for each site.

EVN also provides service and maintenance support across parts of E.ON Drive’s portfolio, including selected hubs originally delivered by other parties. This means its operational role is not limited to the sites it designed or constructed. The service team responds to faults and changing requirements, while evidence from those interventions is shared with the teams responsible for future builds.

That link between operations and delivery has led to practical post-construction changes being incorporated into the new-build specification. It also allows a measure tested at one operational hub to be considered for other live sites where appropriate, rather than waiting for the next construction programme.

Cable theft is one example. EVN and E.ON Drive have introduced real-time cable alerting, alarms, enhanced cable protection and other prevention measures in response to incidents across the network. The purpose is both to protect the existing equipment and to reduce the risk through changes to future designs.

Delivering and Supporting E.ON Drive Infrastructure UK Charging Network

Ryan Smith, Head of Operations and Deployment at E.ON Drive Infrastructure said:
“The EV Network consistently demonstrates what a true partnership should look like: collaborative, responsive, and focused on shared success. Their team takes genuine ownership of our sites, providing exceptional support while continuously feeding technical and operational learnings back into network-wide improvements.

Together, The EV Network and E.ON have also worked closely to address the growing challenge of cable theft, developing innovative solutions such as real-time cable alerting, site sirens, and enhanced theft prevention measures. What sets the partnership apart is the ability of both organisations; we are able to learn from incidents, iterate rapidly, and turn ideas into practical solutions that protect infrastructure and improve reliability.

Combined with their unwavering support, technical expertise, and willingness to go above and beyond, The EV Network has become a trusted partner that continually helps us deliver a better experience for our customers and stakeholders.” 

At Clacton Trade and Leisure Park, EVN uses its Supervisory Control Data Acquisition (SCADA) system to monitor and control parts of the infrastructure remotely. The team can remotely interact with the feeder pillar and power supply and support remote charger resets. This gives the operational team another way to identify and resolve certain faults quickly and can avoid an unnecessary engineer visit.

EVN works with Schneider on the feeder pillar infrastructure used in these solutions. Combining the physical infrastructure with remote monitoring creates a clearer view of site performance and gives the team more options when responding to an issue. The capability is informing discussions with E.ON Drive about smarter feeder pillars and the potential to extend remote services across future charging hubs.


Location & Customer Amenity

The portfolio also shows the importance of location and surrounding amenities. Minworth, located just off the M42 within a busy trade park and alongside a Costa Drive Thru, is one of the strongest-performing hubs across the E.ON Drive hubs to date. Its road access and nearby customer amenities support charging as part of an existing journey rather than requiring a separate destination.

Dunfermline is a different example. The site has more limited space and available power on site, but its single charger has performed strongly alongside an established Tim Hortons destination with regular customer traffic. This supports the case for assessing likely demand, dwell time and surrounding amenities alongside the size and available power of a potential site.

These examples clearly show that hub performance depends on more than just scale. Existing traffic, nearby amenities and the way charging fits into the wider destination can all influence use. They also show why the portfolio model needs enough flexibility to respond to the commercial characteristics of each location.

location and customer amenity


Supporting the Next Phase of Network Growth

EVN continues to deliver against an active pipeline of E.ON Drive sites, with the network expected to reach approximately 112 live chargers and 224 live charging bays by the end of 2026. Further projects are already progressing into 2027.

EVN will continue to deliver the portfolio from development and legal work through construction and commissioning, followed by service, maintenance and remote technical support. This end-to-end role allows insight from operational sites to inform the development and design of the hubs that follow.

As the network grows, the teams will draw on experience from 27 live hubs to identify dependencies earlier, maintain consistent technical and construction standards, and support each site once operational.


Looking to unlock the potential of your site?

Whether you’re a landowner, Charge Point Operator (CPO) or strategic partner, speak to our experts to find out how EVN can support your project from site development and pre-construction through to delivery and handover.

Morgan Barbezat

Marketing Manager

Delivering fast, scalable EV charging infrastructure across the UK, Europe and USA. Contact us today to see how can we help

Let's talk

Call to Action - Main